June Construction Updates

With the civil and structural works complete, we began painting the exterior façade and continued work on the outdoor adventure playground. In the residential section of the project, our team is currently installing doors, windows, and built-in kitchen cabinets.

Exterior facade groove lines

The future outdoor adventure playground

Installation of plywood for auditorium seating area
Wall finishing "pebble wash" in different grey shades at the basement floor

Two-meter wide condo corridors with natural light and ventilation

Testing and commissioning of elevators

Testing and commissioning of elevators